Looking south towards the site of Aylesbury Vale Parkway from the rear of a train. Bridge 179 over the A41 is in the foreground. 1st April 2002. |
Satellite image of the station site before work began. I will post another satellite image of the completed station when it becomes available. (Image courtesy of Google Earth). |
The platform and car park under construction, seen from a route learning train just over a month before the opening date. 11th November 2008. |
Station construction work on 11th November 2008. On the left is the new signal marking the end of the Electric Token Block section from Claydon. |
Artist's impression of Aylesbury Vale Parkway, differing considerably from what is actually being built. At this stage it seems a virtual copy of the building at Warwick Parkway was being proposed. |
The temporary booking office and other buildings in the forecourt. 17th December 2008. |
Interior of the temporary booking office. 17th December 2008. |
Temporary buildings housing staff facilities and a shop. 9th January 2009. |
The car park with about 25 cars in it at 1230 on 17th December 2008. |
The standard Chiltern Railways car park attendant's hut had made an appearance by 10th February 2009. |
New bus shelter in the station forecourt. 10th February 2009. |
The part of the car park not yet in use and the site offices. 10th February 2009. |
The upper part of the car park open and cleared of contractor's huts. 7th June 2009. |
The lower part of the car park with the temporary station buildings removed. 7th June 2009. |
Covered bicycle stand. 7th June 2009. |
Artist's impression of the finished station building. |
South elevation of the new station building. |
The station building under construction. 17th December 2008. |
The station building on 9th January 2009. |
Walls beginning to enclose the frame of the building on 10th February 2009. |
The building looking a little more complete on 21st March 2009. |
The completed building seen from the car park. 7th June 2009. |
The platform side of the building. 7th June 2009. |
The station building seen from the platform. 7th June 2009. |
Station building interior. 7th June 2009. |
Station building interior. 7th June 2009. |
The booking office windows. 7th June 2009. |
Running in board, placed on the non-platform side of the track. 17th December 2008. |
One of the station nameboards. 9th January 2009. |
A disused cattle creep just north of the platform. 9th January 2009. |
The platform looking towards the buffer stops. On the left is the foundation for a waiting shelter. 17th December 2008. |
The waiting shelter, newly erected on 18th December 2008. |
Platform view looking towards Aylesbury. The freight line to Calvert and Claydon passes behind the fence on the right. Space has been left for through platforms to be constructed here should they ever be required as part of the East-West Rail Link. 17th December 2008. |
Looking towards the buffer stops from the end of the seven-car platform. 17th December 2008. |
Looking towards Aylesbury from the platform with one of the DOO mirrors on the right. 9th January 2009. |
The platform, now complete with passenger information system and seats. 7th June 2009. |
The south end of the station showing an arriving train, the junction with the line from Claydon and the starter signal. 17th December 2008. |
Commemorative ticket from the official opening day. |
| |